Project Duration
Stipulated Date of Commencement
December 15 2011
Stipulated Date of Completion /
Likely Date of Completion April 14 2012
Likely Date of Completion April 14 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 48,287,670.00
Awarded for
₹ 29,652,470.00
Contractors
M/s. Godrej & Boyce Mfg. Co. Ltd.
Consultants
M/s. Effective Architectural Services