Project Duration
Stipulated Date of Commencement
November 10 2005
Stipulated Date of Completion /
Likely Date of Completion November 17 2005
Likely Date of Completion November 17 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,465,000.00
Awarded for
₹ 3,229,000.00
Project highlights
Supply of pavers
Contractors
M/s. Basant Floorings Private Limited
Consultants
In-house (GSIDC)
See Similar Projects
Interior Works for Office Premises for Departments / Corporations at EDC, Patto Plaza, Panaji, Goa
View Project
Fabrication and supply of metal cages of size 1.37 m X 1.40 m X 1.22 m.
View Project
Construction of building at Patto with provision for Gas insulated substation Panaji Phase I
View Project