Project Duration
Stipulated Date of Commencement
September 14 2010
Stipulated Date of Completion /
Likely Date of Completion September 13 2011
Likely Date of Completion September 13 2011
Status
Completed
Cost (₹)
Estimated at
₹ 97,704,352.00
Awarded for
₹ 96,298,092.54
Project highlights
Renovation/Refurbishment of existng building
Contractors
M/s. D. S. Contractors Private Limited
Consultants
M/s. Effective Architectural Services
See Similar Projects
Construction of New Panchayat Ghar for Village Panchayat at Siridao-Palem in the Survey no. 40/0 in the Village Siridao, Tiswadi
View Project
Zeutschel Book Scanner.
View Project
Landscaping work in the state of Goa
View Project





