Project Duration
Stipulated Date of Commencement
August 19 2014
Stipulated Date of Completion /
Likely Date of Completion August 18 2017
Likely Date of Completion August 18 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ Rate contract Rs. 3,00,00,000.00
Awarded for
₹ Rate contract Rs. 3,00,00,000.00
Project highlights
Refurbishment of ornamental poles
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
In-house (GSIDC)