Project Duration
Stipulated Date of Commencement
February 21 2021
Stipulated Date of Completion /
Likely Date of Completion April 20 2021
Likely Date of Completion April 20 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,832,140.00
Awarded for
₹ 1,832,000.00
Project highlights
Installtion of Bio Digester Plant for treating kitchen waste from building and for generation of bio gas that will be again used in kitchen for cooking purpose.
Contractors
M/s. Urja Bio System Pvt. Ltd.
Consultants
M/s LKS India Pvt. Ltd.