Project Duration
Stipulated Date of Commencement
February 01 2012
Stipulated Date of Completion /
Likely Date of Completion March 16 2012
Likely Date of Completion March 16 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,00,26,362.00
Awarded for
₹ 5,637,190.00
Contractors
M/s. Siemens Enterprises Communications Pvt. Ltd.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.