Project Duration
Stipulated Date of Commencement
September 15 2011
Stipulated Date of Completion /
Likely Date of Completion January 14 2012
Likely Date of Completion January 14 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 44,92,891.00
Awarded for
₹ 4,693,205.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.