Project Duration
Stipulated Date of Commencement
June 20 2021
Stipulated Date of Completion /
Likely Date of Completion October 17 2021
Likely Date of Completion October 17 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,658,751.00
Awarded for
₹ 11,264,964.00
Project highlights
Electrical wiring, SITC of electrical substation at three existing sheds
1) Organic waste management facility behind Heera petrol pump patto.
2) Waste Management facility opposite LIC building at Patto.
3) Material recovery facility at St. Inez in panaji.
Contractors
M/s. Girish Enterprises Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates
See Similar Projects
Major Repairs to Old Aged Home of IPA Provedoria at Margao, Chinchinim and Majorda : (Phase – I, Majorda)
View Project
Landscaping, Civil, Land Development, Outdoor Lighting and other allied works
View Project
Panaji to Patradevi (Part II) – Chainage 21.90 km. to 43.80 km.
View Project





