Project Duration
Stipulated Date of Commencement
February 16 2010
Stipulated Date of Completion /
Likely Date of Completion August 15 2010
Likely Date of Completion August 15 2010
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,33,96,780.00
Awarded for
₹ 21,149,474.00
Contractors
M/s. Imperial Engineering Co.
Consultants
M/s. Rajiv Khanna & Associates Pvt. Ltd.