Project Duration
Stipulated Date of Commencement
September 29 2013
Stipulated Date of Completion /
Likely Date of Completion December 28 2013
Likely Date of Completion December 28 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,782,048.00
Awarded for
₹ 17,220,980.50
Project highlights
Providing of loose furniture, false ceiling, panelling etc. in the the building.
Contractors
M/s. Floor-Space
Consultants
M/s. Frischmann Prabhu (India) Pvt. Ltd.