Project Duration
Stipulated Date of Commencement
November 17 2014
Stipulated Date of Completion /
Likely Date of Completion January 15 2015
Likely Date of Completion January 15 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,202,417.00
Awarded for
₹ 5,453,760.00
Project highlights
Solid Waste Management during St. Francis Xavier Exposition 2014 – 2015 at Old Goa
Contractors
M/s. Gourish P. Naik
Consultants
In-house (GSIDC)