Project Duration
Stipulated Date of Commencement
December 24 2011
Stipulated Date of Completion /
Likely Date of Completion December 24 2012
Likely Date of Completion December 24 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 47,296,436.00
Awarded for
₹ 55,231,075.81
Project highlights
Providing and fixing of pavers and kerbstones for footpaths, benches, cast iron lamp posts,repairs to storm water drains with covered precast RCC slabs and landscaping at various locations in the jurisdiction of VP Agassaim and VP Neura
Contractors
M/s.M.B Kinlekar
Consultants
M/s. Nitin Arolkar