Project Duration
Stipulated Date of Commencement March 07 2019
Stipulated Date of Completion /
Likely Date of Completion
June 06 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 56,445,324.00
Awarded for ₹ 66,856,773.00

Project highlights

The proposed ground and building is housed as a net area of 9435m2. The building is G+1.
The ground floor comprises of Badminton Hall, having two badminton courts, shops – 8nos., room for wash , store rooms, changing rooms for ladies, gents with attached toilets.
The 1st Floor houses a Gymnasium, Games Room and covered spectators gallery. The Playground is provided with natural turf (Bermuda Grass).

 
Gallery Image
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Gallery Image
Consultants
M/s. Datta kare associates
 
Similar Projects

See Similar Projects

Similar Project

Furnishing Work of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
Similar Project

Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil,Plumbing & Electrical works -Package I- Sattari Taluka – GPS Kodal GPMS Nanoda Bamber GPS Dharkand, GPS Murmunem GPMS Padeli

View Project
Similar Project

Landscaping work.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.