Project Duration
Stipulated Date of Commencement
December 25 2016
Stipulated Date of Completion /
Likely Date of Completion September 24 2017
Likely Date of Completion September 24 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,479,284.00
Awarded for
₹ 44,372,186.00
Project highlights
football ground of size 77.65m x 62.00m with 3.00 mts. warm up area all around the ground with 850 spectator stand capacity. Provision of basket ball court and vollyball court. Also consist of G+1 club house.
Contractors
M/s. Indage Development Construction Pvt. Ltd.
Consultants
M/s. Gurudutt Sanzgiri
See Similar Projects
Supply & Installation of Desks & Chairs for Government Schools/Colleges in the state of Goa- Part-III
View Project
Repairs/Upgradation & Maintenance of Govt. Schools in the state of Goa – Package L (Sattari Taluka) – (GPS Barazan, GPS Khadki, GPS Velge, GPS Khotode)
View Project
Repairs/ upgradation & maintenance of Government School in the State of Goa – GHS Daushire
View Project





