Project Duration
Stipulated Date of Commencement
August 26 2004
Stipulated Date of Completion /
Likely Date of Completion October 30 2004
Likely Date of Completion October 30 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,693,000.00
Awarded for
₹ 15,233,000.00
Project highlights
To restore the structure for Adaptive Re-use of the same. It is located near Panaji Market
Contractors
M/s. M. V. Khandeparkar
Consultants
M/s. Inside Out