Project Duration
Stipulated Date of Commencement
June 16 2013
Stipulated Date of Completion /
Likely Date of Completion June 15 2014
Likely Date of Completion June 15 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ Rate contract
Project highlights
Maintenance works at Goa Medical College and Hospital & Goa Dental College at Bambolim, Goa
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.