Project Duration
Stipulated Date of Commencement
February 12 2015
Stipulated Date of Completion /
Likely Date of Completion August 11 2016
Likely Date of Completion August 11 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 236,589,775.00
Awarded for
₹ 270,000,000.79
Project highlights
120 bedded Ground +1 Hospital
Contractors
M/s. Decor Home (India) Pvt. Ltd.
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.