Project Duration
Stipulated Date of Commencement February 27 2021
Stipulated Date of Completion /
Likely Date of Completion
August 26 2021
Status
100%
Completed
Cost (₹)
Estimated at ₹ 162,970.00
Awarded for ₹ 162,970.00

Project highlights

Maintenance of UPS systems

 
Gallery Image
Contractors
M/s. Vertiv Energy Pvt. Ltd.
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

External electrical work at area around new Library Building and Power supply to new Library Building, GMC Complex, Bambolim, Goa – Supply, laying of 1100 V power supply cable.

View Project
Similar Project

Civil & Plumbing works (Phase-II) – Balance works.

View Project
Similar Project

Upgradation of Pay Ward at Goa Medical College, Bambolim, Goa – Additional furniture works

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.