Project Duration
Stipulated Date of Commencement
February 27 2021
Stipulated Date of Completion /
Likely Date of Completion August 26 2021
Likely Date of Completion August 26 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 162,970.00
Awarded for
₹ 162,970.00
Project highlights
Maintenance of UPS systems
Contractors
M/s. Vertiv Energy Pvt. Ltd.
Consultants
In-house (GSIDC)