Project Duration
Stipulated Date of Commencement January 28 2013
Stipulated Date of Completion /
Likely Date of Completion
January 27 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 3,00,41,753.00
Awarded for ₹ 3,90,22,573.00
 
Gallery Image
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd.
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 

Sub Works

This project involved 2 sub works. The details of the same available below

1

Electrical Works.

100% completed
 
Project Duration
Stipulated Date of Commencement May 26 2013
Stipulated Date of Completion /
Likely Date of Completion
November 25 2013
Status
100%
Completed
Cost (₹)
Estimated at ₹ 23,50,771.00
Awarded for ₹ 23,88,737.00
 
Contractors
Contractors
M/s. Mohan Electricals
Consultants
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
2

HVAC Works.

100% completed
 
Project Duration
Stipulated Date of Commencement September 26 2013
Stipulated Date of Completion /
Likely Date of Completion
January 25 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,324,109.94
Awarded for ₹ 5,899,999.00
 
Contractors
Contractors
M/s. Aprant Motors Pvt. Ltd.
Consultants
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
Similar Projects

See Similar Projects

Similar Project

Upgradation and extension of existing Cottage Hospital at Chicalim, Goa SH: Medical Furniture works

View Project
Similar Project

Upgradation of Ward No.120, 123 and 124 at Goa Medical College and Hospital at Bambolim, Goa – S.H- Supply, Installation, Testing and Commissioning of Anaesthesia Workstation

View Project
Similar Project

Supply, installation, testing and commissioning of transformer yard and diesel generating set.

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.