Project Duration
Stipulated Date of Commencement
January 17 2014
Stipulated Date of Completion /
Likely Date of Completion March 17 2014
Likely Date of Completion March 17 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 910,000.00
Awarded for
₹ 1,000,000.00
Contractors
M/S. PRUDENT MANAGEMENT SOLUTIONS
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.