Project Duration
Stipulated Date of Commencement
February 07 2019
Stipulated Date of Completion /
Likely Date of Completion May 06 2019
Likely Date of Completion May 06 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,935,265.00
Awarded for
₹ 5,028,800.00
Project highlights
the project involved providing stainless steel 2 seaters at various location of GMC.