Project Duration
Stipulated Date of Commencement
February 06 2014
Stipulated Date of Completion /
Likely Date of Completion April 06 2014
Likely Date of Completion April 06 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 17,479,000.00
Awarded for
₹ 17,479,000.00
Contractors
M/S. PHILIPS ELECTRONICS INDIA LTD
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Electrical works.
View Project
Major maintenance works at Goa Medical College and Hospital & Goa Dental College at Bambolim, Goa
View Project
Supply & Installation of Lead Doors & Lead Glass
View Project