Project Duration
Stipulated Date of Commencement
December 18 2007
Stipulated Date of Completion /
Likely Date of Completion March 01 2008
Likely Date of Completion March 01 2008
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,667,482.00
Awarded for
₹ 2,508,525.00
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
See Similar Projects
Providing of split air conditioners.
View Project
Electrical work.
View Project
Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa S.H.: Supply, Installation, Testing & Commissioning of 500KVA DG set at North Goa District Hospital, Mapusa
View Project