Project Duration
Stipulated Date of Commencement
June 16 2006
Stipulated Date of Completion /
Likely Date of Completion April 15 2007
Likely Date of Completion April 15 2007
Status
100%
Completed
Cost (₹)
Estimated at
₹ 45,331,777.00
Awarded for
₹ 43,374,376.00
Project highlights
Power upgradation work includes utility buiding, 33 KV substation, HT panels, LT panels and 11 KV ring main unit (RMU) and cabling.
Contractors
M/s. ABB Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
See Similar Projects
Major Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa SH : Maintenance Contract for Cold Storages installed in Blood Bank, Microbiology Department and Central Pharmacy in GMC Hospital Complex Bambolim for three years
View Project
Fire fighting, fire alarm and PA System works
View Project
Construction of Lecture Hall at Goa Medical College & Hospital at Bambolim, Goa – Civil, Plumbing, Electrical, Lift, Fire Fighting & HVAC works.
View Project