Project Duration
Stipulated Date of Commencement June 16 2006
Stipulated Date of Completion /
Likely Date of Completion
April 15 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 45,331,777.00
Awarded for ₹ 43,374,376.00

Project highlights

Power upgradation work includes utility buiding, 33 KV substation, HT panels, LT panels and 11 KV ring main unit (RMU) and cabling.

 
Gallery Image
Contractors
M/s. ABB Ltd.
Gallery Image
Consultants
M/s. FP INDIA PROJECT MANAGEMENT CONSULTANCY SERVCIES PVT. LTD
 
Similar Projects

See Similar Projects

Similar Project

Procurement of Equipment for the Burns Unit (New Ward 118), Department of Plastic Surgery, Goa Medical College, Bambolim –Goa -SH-Supply, Installation, Testing and Commissioning of Central Nursing Station monitor and Multichannel monitors (5 channels with IBP Monitoring)

View Project
Similar Project

Major Maintenance Work of Goa Medical College & Hospital at Bambolim, Goa SH : Operation & maintenance contract for Centralized Air Conditioning (AC) system of GMC at Bambolim, Goa for 3 years (2020-2023)

View Project
Similar Project

Lift work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.