Project Duration
Stipulated Date of Commencement
November 09 2018
Stipulated Date of Completion /
Likely Date of Completion March 08 2019
Likely Date of Completion March 08 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 22,119,472.00
Awarded for
₹ 17,220,494.00
Project highlights
Providing furniture and interior works at RMO Hostel at GMC.
Contractors
M/s.Virender Kumar & Co.
Consultants
M/s. Frishmann Prabhu (I) Pvt. Ltd.