Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion June 21 2014
Likely Date of Completion June 21 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,153,346.00
Awarded for
₹ 5,440,968.00
Project highlights
Repairs to Library Block of Goa Medical College
Contractors
M/s. Floor-Space
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd.
See Similar Projects
Supply of Syringe pumps
View Project
Upgradation of Ward Nos.120, 123, 124, Staff Rest Rooms (Old Garage) and other miscellaneous works at Goa Medical College and Hospital at Bambolim, Goa
View Project
Maintenance/Renovation works of Community Health Centre at Valpoi . Maintenance Contract for 2 Nos lift of make M/s. Thyssenkrupp Elevators India for a period of three years.
View Project