Project Duration
Stipulated Date of Commencement
December 23 2005
Stipulated Date of Completion /
Likely Date of Completion February 10 2006
Likely Date of Completion February 10 2006
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,260,953.00
Awarded for
₹ 1,391,854.80
Project highlights
Repairing of existing road by cleaning, levelling, filling of pot holes, constructing S.W.D., catch pits, inspection chambers, precast concrete pipes, etc.
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd