Project Duration
Stipulated Date of Commencement January 08 2006
Stipulated Date of Completion /
Likely Date of Completion
February 15 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 875,750.00
Awarded for ₹ 693,650.00

Project highlights

Providing power supply to the new Library building from the transformer near Mortuary buidlign, GMC Complex, procuring and laying of cable.

 
Gallery Image
Contractors
M/s. Ohm Engineers
Gallery Image
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 
Similar Projects

See Similar Projects

Similar Project

Upgradation and extension of existing Cottage Hospital at Chicalim, Goa SH: Medical Furniture works

View Project
Similar Project

Supply, installation, testing and commissioning of 15 passenger cum bed lift for T. B. and chest diseases hospital, St. Inez, Goa.

View Project
Similar Project

Landscape work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.