Project Duration
Stipulated Date of Commencement
September 12 2012
Stipulated Date of Completion /
Likely Date of Completion August 03 2013
Likely Date of Completion August 03 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 16,433,755.00
Awarded for
₹ 16,248,000.00
Project highlights
Furniture works
Contractors
M/s. Floor-Space
Consultants
M/s Effective Architectural Services