Project Duration
Stipulated Date of Commencement
October 28 2022
Stipulated Date of Completion /
Likely Date of Completion June 08 2023
Likely Date of Completion June 08 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,244,707.22
Awarded for
₹ 21,777,600.16
Project highlights
Roofing works at Goa Medical College & Hospital
Contractors
M/s. Adhav Infra Projects Pvt. Ltd
Consultants
In-house (GSIDC)