Project Duration
Stipulated Date of Commencement January 20 2011
Stipulated Date of Completion /
Likely Date of Completion
May 14 2011
Status
100%
Completed
Cost (₹)
Estimated at ₹ 40,22,007.00
Awarded for ₹ 38,60,325.00
 
Gallery Image
Contractors
M/s. Hi-Tech Engineering Works
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Cardiac output Monitoring System

View Project
Similar Project

Major Maintenance Work of Goa Medical College & Hospital at Bambolim, Goa SH : Operation & maintenance contract for Centralized Air Conditioning (AC) system of GMC at Bambolim, Goa for 3 years (2020-2023)

View Project
Similar Project

Mortuary cabinet work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.