Project Duration
Stipulated Date of Commencement
August 31 2013
Stipulated Date of Completion /
Likely Date of Completion September 30 2013
Likely Date of Completion September 30 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,044,105.30
Awarded for
₹ 1,095,570.00
Contractors
M/s. Paulbern Enterprises
Consultants
Datta Kare Associates
See Similar Projects
Interior and Furniture works
View Project
Maintenance work of Goa Medical College & Hospital and Goa Dental College at Bambolim, Goa. S.H.: Maintenance Contract for 4 nos. of Emerson make 30 KVA UPS systems installed for Modular OTs 1-4 at Goa Medical College and Hospital, Bambolim for a period of three years.
View Project
Additions and Alterations to ground floor area of Foyer Block at GMC, Complex, Bambolim, Goa.
View Project