Project Duration
Stipulated Date of Commencement June 28 2012
Stipulated Date of Completion /
Likely Date of Completion
July 27 2012
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,408,454.00
Awarded for ₹ 3,977,777.00
 
Gallery Image
Contractors
M/s. Harshada Trading Company
Gallery Image
Consultants
M/s. Keni & D’Souza
 
Similar Projects

See Similar Projects

Similar Project

Supply, installation, testing and commissioning of transformer yard and diesel generating set.

View Project
Similar Project

Rural Medical Dispensary at Keri.

View Project
Similar Project

Maintenance works at Goa Medical College and Hospital S.H.: Maintenance Contract for 4 nos. of Emerson make 30 KVA UPS systems installed for Modular OTs 1-4 at Goa Medical College and Hospital, Bambolim for six months

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.