Project Duration
Stipulated Date of Commencement
September 25 2021
Stipulated Date of Completion /
Likely Date of Completion October 02 2021
Likely Date of Completion October 02 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 561,600.00
Awarded for
₹ 561,600.00
Project highlights
Supply and Installation of Oxygen Jumbo cylinders for gas manifold
Contractors
M/s. Scoop Industries Pvt. Ltd.
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.