Project Duration
Stipulated Date of Commencement
May 03 2019
Stipulated Date of Completion /
Likely Date of Completion March 25 2019
Likely Date of Completion March 25 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 110,300.00
Awarded for
₹ 114,925.00
Contractors
M/s.Vighneshwar Airconditioning Pvt Ltd
Consultants
In-house (GSIDC)