Project Duration
Stipulated Date of Commencement
August 19 2019
Stipulated Date of Completion /
Likely Date of Completion August 09 2019
Likely Date of Completion August 09 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 229,682.00
Awarded for
₹ 228,630.00
Contractors
M/S. Vighneshwar Airconditioning Pvt Ltd
Consultants
In-house (GSIDC)
See Similar Projects
Demolition and construction of hospital and hostel at Mandur, Goa
View Project
Construction of Primary Health Centre at Navelim, Margao, Goa. – Interior Work.
View Project
Supply Installation Testing & Commissioning of incinerators.
View Project