Project Duration
Stipulated Date of Commencement
May 07 2014
Stipulated Date of Completion /
Likely Date of Completion April 09 2014
Likely Date of Completion April 09 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,057,180.00
Awarded for
₹ 1,142,198.72
Project highlights
Demolition of old dilipidated structures
Contractors
M/s. R.S.Lawande
Consultants
M/s. Structwel Designers & Consultants Pvt. Ltd.