Project Duration
Stipulated Date of Commencement
August 18 2009
Stipulated Date of Completion /
Likely Date of Completion October 17 2009
Likely Date of Completion October 17 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,750,000.00
Awarded for
₹ 5,300,000.00
Contractors
M/s. Jindal Photo Ltd.
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.