Project Duration
Stipulated Date of Commencement March 26 2007
Stipulated Date of Completion /
Likely Date of Completion
June 25 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 17,671,482.00
Awarded for ₹ 18,007,783.00
 
Gallery Image
Contractors
M/s. MGI (I) Pvt. Ltd.
Gallery Image
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa – SH: Dismantling and buy back of existing Sewage Treatment Plant (STP) and Design, Supply, Installation, Testing and Commissioning of new 30 KLD STP at Community Health Centre, Canacona – Goa

View Project
Similar Project

Construction of New Premises for Community Health Centre at Tuem, Pernem Goa and Major Civil works sanctioned under NRHM – ROP 2012-13.: Phase I: Repair and upgradation works of existing community health centre under NRHM

View Project
Similar Project

Interior work

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.