Project Duration
Stipulated Date of Commencement March 08 2019
Stipulated Date of Completion /
Likely Date of Completion
May 07 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 4,305,526.00
Awarded for ₹ 4,299,500.00

Project highlights

Supply, Installation, Testing & Commissioning of 500KVA DG set

 
Gallery Image
Contractors
M/S. Power Engineering (India) Pvt Ltd
Gallery Image
Consultants
In-house (GSIDC)
 
Similar Projects

See Similar Projects

Similar Project

Improving & Revamping of Water supply, Power supply & Sewerage Network at Goa Medical College & Hospital, Bambolim-Goa – Phase II – SH – Fire Detection System I

View Project
Similar Project

Electrical & Fire Fighting work.

View Project
Similar Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in South Goa S.H.: Maintenance Contract for the UPS systems installed at Upgraded Cottage Hospital, Chicalim for a period of three years (2019-2022)

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.