Project Duration
Stipulated Date of Commencement
December 17 2008
Stipulated Date of Completion /
Likely Date of Completion February 16 2009
Likely Date of Completion February 16 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 12,15,500.00
Awarded for
₹ 1,210,124.00
Contractors
M/s. Medraid Systems
Consultants
M/s. Consulting Engineering Services Pvt. Ltd.