Project Duration
Stipulated Date of Commencement
September 22 2011
Stipulated Date of Completion /
Likely Date of Completion June 21 2012
Likely Date of Completion June 21 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,062,925.00
Awarded for
₹ 6669089.99
Project highlights
Construction of Anganwadi Centres
Contractors
M/s. Ask Developers
Consultants
M/s. Datta Kare Associates