Project Duration
Stipulated Date of Commencement
August 15 2018
Stipulated Date of Completion /
Likely Date of Completion August 14 2019
Likely Date of Completion August 14 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,000,000.00
Awarded for
₹ 5,000,000.00
Project highlights
furniture supply
Contractors
M/s.Amardeep Designs Pvt ltd
Consultants
In-house (GSIDC)