Project Duration
Stipulated Date of Commencement
May 23 2013
Stipulated Date of Completion /
Likely Date of Completion August 22 2013
Likely Date of Completion August 22 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 6,265,380.00
Awarded for
₹ 7,015,854.00
Project highlights
School Building with 4 classrooms of international size 60 sq. m
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Datta Kare Associates
See Similar Projects
Repairs/Upgradation & Maintenance of Government schools in the State of Goa – CIVIL PLUMBING & ELECTRICAL WORKS works-Bicholim Taluka – Package L (GPS Tale Pale & GPS Ghongree Maina Navelim)
View Project
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka- Package C (G.P.S Gaokarwada Mayem, G.P.S Shirodawadi Mulgao, G.P.S. Haturli Mayem)
View Project
Urgent repair works of Government Schools in the State of Goa – Civil,Plumbing and Electrical works including strengthening of Polling booth -Package IV (Sattari Taluka)
View Project