Project Duration
Stipulated Date of Commencement
January 31 2005
Stipulated Date of Completion /
Likely Date of Completion July 30 2005
Likely Date of Completion July 30 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,600,000.00
Awarded for
₹ 4,596,000.00
Project highlights
Construction of a building for Government High School consisting of six classrooms and one library, one laboratory, one staff room, toilets for boys and girls
Contractors
M/s. Coastal Builders
Consultants
M/s. Kuvelkar Salkar Associates
See Similar Projects
Repairs / Upgradation & Maintenance of Government High Schools in the State of Goa – GHS Netravali
View Project
Furnishing Work of Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.
View Project
Repairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Bicholim Taluka – Package F (G.P.S. Kelbaiwada Mayem, G.P.S. Borde, G.P.S. Bhavkai Mayem, G.P.S. Haldonwadi Mayem ).
View Project