Project Duration
Stipulated Date of Commencement
January 31 2005
Stipulated Date of Completion /
Likely Date of Completion July 30 2005
Likely Date of Completion July 30 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,600,000.00
Awarded for
₹ 4,596,000.00
Project highlights
Construction of a building for Government High School consisting of six classrooms and one library, one laboratory, one staff room, toilets for boys and girls
Contractors
M/s. Coastal Builders
Consultants
M/s. Kuvelkar Salkar Associates
See Similar Projects
Construction of National Institute of Water Sports Campus at Caranzalem, Goa – Balance – Civil, Plumbing, Electrical, Fire Fighting and HVAC works
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa – Pernem Taluka: Package – V (GPS Tiwade Dhargal, GPS Chandel, GPS Madkai Ozari, GPS Varkhand, GPS Bhatpavni, GPS Patradevi, GPS Fakirpata Torse, GPS Tulaskarwadi)
View Project
Supply, Installation, Testing & Commissioning of CCTV & PA System
View Project