Project Duration
Stipulated Date of Commencement
January 31 2005
Stipulated Date of Completion /
Likely Date of Completion July 30 2005
Likely Date of Completion July 30 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,600,000.00
Awarded for
₹ 4,596,000.00
Project highlights
Construction of a building for Government High School consisting of six classrooms and one library, one laboratory, one staff room, toilets for boys and girls
Contractors
M/s. Coastal Builders
Consultants
M/s. Kuvelkar Salkar Associates