Project Duration
Stipulated Date of Commencement
March 04 2014
Stipulated Date of Completion /
Likely Date of Completion September 03 2014
Likely Date of Completion September 03 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 15,000,000.00
Awarded for
₹ 15,000,000.00
Project highlights
Repairs and renovation of roofing, to 10 number of Government Primary schools in Quepem Taluka in this package.
Contractors
M/s.K G Thomas
Consultants
M/s.Manoj Amshekar