Project Duration
Stipulated Date of Commencement March 01 2019
Stipulated Date of Completion /
Likely Date of Completion
June 29 2019
Status
100%
Completed
Cost (₹)
Estimated at ₹ 6,461,990.00
Awarded for ₹ 5,800,069.00

Project highlights

interior & Miscellaneous works in Administration Block

 
Gallery Image
Contractors
M/S.Creation Interior Contractor
Gallery Image
Consultants
M/s. F P Project Management Pvt. Ltd.
 
Similar Projects

See Similar Projects

Similar Project

Soft Landscaping works

View Project
Similar Project

Construction of Compound Wall for Ashram school under centrally sponsored scheme of Ministry of Tribal Affairs at “MOSHIPHOND” in the Land under Survey no. 20/0 in the Village Poinguinim of Canacona Taluka.

View Project
Similar Project

Construction of Anganwadi Centres from NABARD Assistance – Package II (GPS Sangao Ozari, GPS Sakral Torse).

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.