Project Duration
Stipulated Date of Commencement
June 20 2022
Stipulated Date of Completion /
Likely Date of Completion January 29 2023
Likely Date of Completion January 29 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 10,661,942.00
Awarded for
₹ 12,870,005.18
Project highlights
Repairs/Upgradation & Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates