Project Duration
Stipulated Date of Commencement
October 28 2016
Stipulated Date of Completion /
Likely Date of Completion April 27 2017
Likely Date of Completion April 27 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 9,721,364.00
Awarded for
₹ 11,039,275.00
Project highlights
Repair & upgradation work of the school building, including roofing, painting, tilling, plumbing work etc