Project Duration
Stipulated Date of Commencement
May 07 2020
Stipulated Date of Completion /
Likely Date of Completion February 29 2024
Likely Date of Completion February 29 2024
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,046,162.00
Awarded for
₹ 14,097,778.40
Project highlights
The scope of work includes supply of readymade furnitures, workstations, etc.
Contractors
M/s. Harshada Trading Company
Consultants
M/s. M:OFA Studios Pvt. Ltd.